Plan warning issue

118 views

I can't modify the date of the plan. When i chage the date, the planing warning appears (it says: you moved '......'. this is before the plan start date. Do you want to continue?) and i can proceed since the OK button doesn't work at all.
What is the problem and is there any way i can remove this warnin function from seettings?

Addition: I coudn't figure out how to reply here, so i edit the question

It is not before the proejct start date, there are mamy other tasks before it.

"If you create a Task and set its Start date prior to the Plan Start date (say 18 Nov 2014), this popup will appear. If you click on OK, it will shift your Task Start date but not the Plan Start Date. Those changes will be limited only upto that task"
 The problem is that it doesn't react to OK function i.e. it is not working (CANCEL works) though
sometimes it works....

asked Nov 20, 2014 by Alova (120 points)
edited Nov 20, 2014 by Alova

1 Answer

0 votes
Hello,
 
Thank you for approaching us.
 
In Ganib the Plan dates are set at the time of Project creation. For instance, if you have set Project Start Date as 20 Nov 2014, the Plan Start date will also be 20 Nov 2014.
 
If you create a Task and set its Start date prior to the Plan Start date (say 18 Nov 2014), this popup will appear. If you click on OK, it will shift your Task Start date but not the Plan Start Date. Those changes will be limited only upto that task.
 
To know how to change or modify the Plan Start dates, Please refer below link:
 
If you are facing any other issues, please feel free to contact us. We are happy to help you.
 
Thanks,

Jaclyn

Jaclyn N,
Ganib Support Team, Ganib Inc.