Hi,

I have a question regarding the work hours with the Task that Planned in Gantt Chart Plan.

e.g scenario

1) I Plan > Task1 on 14 Nov 2014 with 8 hrs/day and I assigned to a resource called John.

2) Assuming John used 10 hours on that Task1, initially he will key-in 10 hours into the Timesheet Weekly. But in real case, John is not finishing the Task1 as it was assigned or may be John just done around 50% of the Task1.

3) Eventually, when I check the Plan it written 100% completed. Although John actually not completed yet on the Task1 and just because John fulfilled the 8 hrs/day.

So is there anyway to turn it not to tied with the completion percentage until John really checked on the completed status?

 

Please help.
asked Nov 14, 2014 by kccy2020 (300 points)

1 Answer

0 votes

Hello,

Thank you for approaching us.

Right now, the functionality is such that whatever Working hours you have defined for a particular task, and the resource assigned to that task captures that many hours, the task automatically gets completed.


Below link gives you a detailed report of how and where the working hours from the Timesheet Weekly View are reflected. Please refer:
http://help.ganib.com/faq/content/20/288/en/tracked-time-reflections-via-timesheet-weekly-view.html

If you are facing any other issues than this, Please feel free to contact us. We are happy to help you.

Thanks,

Jaclyn

Jaclyn N,
Ganib Support Team, Ganib Inc.