Hi,
I have a question regarding the work hours with the Task that Planned in Gantt Chart Plan.
e.g scenario
1) I Plan > Task1 on 14 Nov 2014 with 8 hrs/day and I assigned to a resource called John.
2) Assuming John used 10 hours on that Task1, initially he will key-in 10 hours into the Timesheet Weekly. But in real case, John is not finishing the Task1 as it was assigned or may be John just done around 50% of the Task1.
3) Eventually, when I check the Plan it written 100% completed. Although John actually not completed yet on the Task1 and just because John fulfilled the 8 hrs/day.
So is there anyway to turn it not to tied with the completion percentage until John really checked on the completed status?
Please help.