Additional/Extra work effort of the tasks getting revised the complete plan

13,722 views

Ganib Version 5.0

------------------------

1. The following tasks are added to the plan:

Task Work Duration Start Finish Completed % Complete Calculation Type Actual Start Actual Finish
  Task1 18 hrs 2.25 days 18 Sep, 2014 22 Sep, 2014 18 hrs 100% Fixed Units, Effort Driven 18 Sep, 2014 22 Sep, 2014
  Task2 12 hrs 1.5 days 23 Sep, 2014 24 Sep, 2014 0 hrs 0% Fixed Units, Effort Driven    
  Task3 12 hrs 1.5 days 25 Sep, 2014 26 Sep, 2014 0 hrs 0% Fixed Units, Effort Driven    
  Task4 10 hrs 10 hrs 29 Sep, 2014 30 Sep, 2014 0 hrs 0% Fixed Units, Effort Driven    
  Task5 14 hrs 14 hrs 30 Sep, 2014 1 Oct, 2014 0 hrs 0% Fixed Units, Effort Driven    
  Task6 10 hrs 10 hrs 6 Oct, 2014 7 Oct, 2014 0 hrs 0% Fixed Units, Effort Driven    

In the above plan, planned duration of Task1 is 16 hrs, resource took 2 hrs extra to complete this task and total hours to complete this task is 18 hours. With this extra 2 hours, the actual finish date is moved to next day even though resources entered 9 hrs/day and also it is not getting organized the rest of the tasks appropriately. Still there are 6hrs left on 22 Sep but the next task moved to 23 Sep.

The planned are getting overwritten with actuals. How to retain the planned and actuals?

asked Sep 22, 2014 by gogineni (480 points)

2 Answers

0 votes
Hello,
 
Thank you for approaching us.
 
We are aware of this problem (Known Issue) and Engineering is already working on this bug. Most Probably this fix can be released in next release patch which is held in next couple of days
 
I will update here again after the bug is fixed..
 
If you are having any further queries on this, Please feel free to contact us. We are happy to help you.
 
Thanks,

Jaclyn

Jaclyn N,
Ganib Support Team, Ganib Inc.
Free Signup | Free Download | Documentation
Skype ID: ganib.support
Email: support@ganib.com

 

answered Sep 23, 2014 by Jaclyn (18,310 points)
0 votes

Hello,

Thank you for being with us this far.

The issue that you reported above has been resolved by our team and the fixes are released on SAAS version.
You can create a SAAS account for free by visiting the link http://www.ganib.com/. These fixes will be available with the Open Source version in the next couple of weeks.

Besides this, we have introduced two more new features of User Inheritance and WYSIWYG Editor for Pages. Here are the links which will let you know more about both the features:

User Inheritance: http://help.ganib.com/faq/content/25/284/en/user-inheritance.html
WYSIWYG Editor: http://help.ganib.com/faq/content/14/285/en/wysiwyg-editor.html


If you are still facing any issues, Please feel free to contact us. We are happy to help you.

Thanks,

Jaclyn

Jaclyn N,
Ganib Support Team, Ganib Inc.
Free Signup | Free Download | Documentation
Skype ID: ganib.support
Email: support@ganib.com

 

answered Sep 30, 2014 by Jaclyn (18,310 points)
...